Morrow Meadows

Hyperion Digester

Project Details

Date: May 2017

Location: Playa del Rey, CA

Size: 28 MW

Attributes: Design Build,

Share Project

This Combined cycle power generation facility uses treated, clean digester gas, blended with natural gas to power turbine generators.  Morrow Meadows Corporation is proud to have been the electrical contractor on this fast paced project.  We manned this project with 2 shifts, 7 days a week for 6 months to meet the demanding schedule to bring this critical power facility online.  We are especially proud of our very own Jarrod Tiner, who received the Terry V Perkins Memorial Safety Award from the National Electrical Contractors Association in May of this year for his outstanding work and leadership on this project.